Legislation
(Edited and posted by
John Antell)
Sale of Goods Act 1979
Supply of Goods and Services Act
1982
Unfair Contract Terms Act 1977
Case Law
SAM Business Systems Limited v
Hedley & Co.
[2002] EWHC 2733
Information and Communications
Technology:
Case Note - SAM Business
Systems Limited v Hedley & Co.
27 Dec 2002
This case note first appeared on the NIPC website
As well as being of local interest to Northern practitioners in that
the defendants were Lancashire stockbrokers represented by
Rawsthorns, this judgment is noteworthy for 4 important points. The
first is Judge Bowsher's assertion that if a software system is sold
as tried and tested it should not have any bugs at all, and, if
there are any, such bugs should be regarded as defects. The second
is the balancing exercise
by which His Honour determined whether an "entire agreement" clause
satisfies the requirement of reasonableness under the
Unfair Contract Terms Act 1977 ("UCTA").
The third was a reminder that a customer may reject a computer
system only if he gives timely and unequivocal notice and does so
before he gains any substantial benefit from the system. The fourth
and last point is the judge made it clear that a
supplier cannot charge a maintenance fee for correcting bugs in a
tried and tested system that should not have been there in the first
place.
The
Dispute
This was a claim by a small systems house against a medium size firm of
stockbrokers for £310,509.84 plus interest claimed in respect of licence
fees and post-installation maintenance and other services for an
applications software package. The stockbrokers, who had already paid
£184,605.32 to their supplier, counterclaimed for their money back plus
damages for the increased cost of working, write-offs, fines and
additional charges, mitigation costs, and loss of profits which amounted to
£789,658.44 plus interest.
The Facts
This was in a sense a Y2K action. The software package that gave rise to the litigation had been ordered towards the end of 1999 because the defendants feared that their otherwise serviceable if old-fashioned DOS based transaction processing system would not function properly in the new millennium. The claimant's software was a ready-made package of software modules for stockbrokers and others dealing in stocks and shares. Its functions included processing and settling transactions in buying and selling shares, accounting for clients' money, and communicating with CREST. The brokers first approached the claimant in July 1999 who demonstrated its system to them in September. In its brochure6 and in subsequent correspondence as well as in pre-contract discussions, the supplier made various claims for the suitability and reliability of its product and promised a money back guarantee should the brokers be dissatisfied. Those representations and promise helped to persuade the brokers to acquire it. Licence and maintenance agreements were signed in October and the software was delivered in December 1999. Serious problems occurred almost immediately after installation. Some of those problems were fixed quite quickly but others arose throughout 2000. At least one of those problems brought the defendants into conflict with their regulator, the SFA. In January 2001, the defendants decided to stop using the system and to outsource their back office. They did not tell the supplier of their decision until early in February. Outsourcing commenced in May 2001. The claimant issued proceedings were issued in June 2001. The brokers counterclaimed for the damages mentioned above on the grounds of misrepresentations and breach of contract. They pleaded that they were entitled to rescind the contracts, alternatively, to reject the system or in the further alternative to treat the agreements as having been repudiated by the supplier.
The Contracts
The parties entered into 2 written agreements, namely a licence and a
maintenance agreement, which were signed by the supplier on the 12 and by
the brokers on the 18 Oct 1999 respectively.
The Licence
The licence required a licence fee of £116,000 to be paid at 3 stages:
|
|
£58,000 on signature |
|
|
£29,000 on installation, and |
|
|
£29,000 on completion. |
"Completion" was to have taken place 30 days after the supplier had informed the customer in writing that the software had been installed unless, within that 30 day period the customer, informed the supplier of instances where the software failed certain defined acceptance criteria. Delivery and installation were to take place within the later of 30 days after suitable computing environments have been made available to the supplier by the customer or 30 days from signature of this agreement. The agreement set out detailed machinery for the customer to make acceptance tests and, if not satisfied, to reject the software. The supplier, on the other hand, had the right to demand arbitration if not satisfied that rejection was justified. The licence also contained "entire agreement", exclusion and limitation of liability clauses. In addition to the express terms, the judge accepted the defendants' submission that the following implied terms had been imported into the licence agreement subject only to whether they could be negatived by the entire agreement clause:
"a) [the claimant's software] would be
constructed and installed at [the defendants'] premises with all proper and
professional care and skill;
b) [the software] would be reasonably fit for the purposes for which [the
defendants] required it;
c) [the software] would be of satisfactory quality;
d) [the software] would properly and efficiently perform all the required
functions;
e) [the software] would perform all such functions in such a way as to
enable [the defendant firm] to fulfil its professional obligations to its
clients and its statutory duties as required by the FSA;
f) [the claimant] would efficiently carry out the migration and processing
of the [existing system's] data."
These submissions were based on s. 4 and s. 13 of the Supply of Goods and Services Act, 1982 and the judgment of Sir Ian Glidewell in St. Alban's DC v. International Computers Limited.
The
Maintenance Agreement
By the maintenance agreement, the claimant undertook to provide:
|
|
diagnosis and correction of reproducible software errors during normal office hours; |
|
|
telephone support of the application software to 2 named operators or their alternates during normal office hours; |
|
|
delivery by remote link of application software maintenance, releases and corrections as they become available for the application software; |
|
|
periodic documentation updates as they become available for the application software; and |
|
|
version control of the application software. |
The agreement was to come into effect as soon as the licence had been executed. It was to remain in force for an initial term of 12 months (unless the licence was terminated by reason of the supplier's breach in which case the maintenance agreement would also come to an) and thereafter from year to year unless terminated upon 6 months notice by either party.
The Judgment
It was
common ground that "completion" as defined by the licence agreement had
never taken place. However, neither party had invoked the dispute resolution
procedure. The judge dealt first with the counterclaim, which required him
to decide whether the claimant could rely on the "whole agreement" clause to
defeat the misrepresentation claim, and the limitation clauses to defeat the
breach of contract claim. His Honour found that those clauses did satisfy
the requirement of reasonableness and that they effectively excluded the
claims for misrepresentation and breach of contract. As to the claim, the
judge found that the defendants had made lengthy efforts over a year to
co-operate with the supplier to get the package to work
and that they had acted perfectly reasonably at the end of that year in
saying that they were not going to try any further to get the software to
work but that did not give them the right to reject the package. Were such
relief to be granted:
"[it] would mean that Hedley's get use of [the software] for 17 months for nothing and also get damages for defects in the system. That cannot be right. If [the defendants] had not had [the software] the firm would have been out of business. The contract gave [the defendants] the opportunity to get their money back if they went through a specified process. If they had gone through that process they would not have had 17 months use of [the software]. They did not go through that process."
The judge
found that the claimant was entitled to the payments due under the first and
second stages of the licence agreement but not the third because completion
had not occurred. He also found that it was entitled to some maintenance
charges but not for the costs of putting right bugs in the software that
should never have been there in the first place. As the defendants had
already paid £183,893.27 under the licence and
maintenance agreements the only sum due to the claimant was a small balance
of £8,773.73 in respect of maintenance plus interest of £1,077.89 charged at
8% over 12 months. His Honour made no order for costs.
Reasonableness of the Exceptions Clauses
The judge's starting point was that the defendants needed a Y2K compliant
system and that could only get one on the claimant's terms. Other suppliers
similar inserted exclusion and limitation clauses into their contracts. Such
terms were necessary to enable suppliers to carry on business. In the
judge's words:
"Although it has not been said in so many terms, [the supplier's] attitude seems to be, "We did not have to take on this contract. Having taken it on our terms, why should the contract be rewritten to expose us to a huge risk and possibly put us out of business?" That is a freedom of contract attitude that would have been entirely acceptable in the nineteenth and early twentieth centuries. Can it survive since Parliament intervened at the behest of the Law Commission in 1977?"
In His
Honour's view it could. The supplier did not abdicate all responsibility as
it offered customers 'a standard money back guarantee on licence' if they
were dissatisfied with the package. The judge made it clear that he would
have regarded the exclusion of liability and entire agreement clauses as
quite unreasonable had there been no such guarantee though he would have
regarded a limitation of liability to
the amount of money paid under the licence agreement as reasonable. But on
the evidence before him and in all the circumstances to which he had
referred (which would not necessarily exist with other contracts signed on
the same terms) he found that all of the terms to which objection was taken
in the contract were reasonable. The parties were of equal bargaining power
in terms of their relative size and resources. The defendants were in a
difficult position of their own making because of their lateness in tackling
the problem of Y2K compliance. The evidence from the supplier was that other
companies like theirs had similar exclusion clauses. The defendants did not
even try to negotiate for terms more favourable to them.
Interrelation between Exceptions Clauses and Maintenance Agreements
As has been pointed out above, the judge expressed the view early in this
judgment that software that is sold as tried and tested should not have any
bugs at all but, if it does, such bugs should be regarded as defects. It
followed that a supplier has a duty to put right such defects at his own
expense even if he excludes or limits his liability by means of an
exceptions clause:
"I cannot see that it is right that [the
claimant] should be paid for putting right a defect in respect of which they
have excluded liability to pay damages. Of course, any product, whether it
be a motor car, or a washing machine, or computer software, may, after
working well to start with, then develop faults and faults arising in that
way, provided they did not exist in a hidden form on delivery, would be the
proper subject of a maintenance agreement. But no consumer would or should
accept liability to pay for rectification of defects existing in goods on
delivery even if there was no contractual liability on the part of the
supplier to pay damages arising out of those defects. If a company supplies
to a factory a power unit that from the outset does not work, the supplier
may be able to sustain a case that he cannot be sued because of his
exclusion clauses, but he could not conceivably charge for making it work
under a maintenance contract. Exclusion clauses exclude liability for breach
of contract: they do not amount to an agreement that performance has been
given by providing equipment that is fit to
be maintained: nor do they amount to an agreement that the purchaser should
pay for any efforts made by the supplier to put right the defects."
Applying that rule the judge disallowed most of the claimant's charges for work done under the maintenance agreement.
Comment
There are 2 important lessons from this judgment. First, it showed that
litigation in the Technology and Construction Court is not always the most
cost-effective way of resolving computer supply disputes. Even though this
case had been one of the least painful computer supply cases in that it came
on for trial relatively quickly it still lasted for 12 days not counting the
handing down of judgment. With silks, juniors and experts on both sides, the
costs must have been horrendous. At the end of this very expensive process
the claimant was awarded less than £10,000 in damages. This complex dispute
boiled down to whether the supplier could rely on the contract terms to
limit its liability and recover under the maintenance agreement the costs of
correcting bugs in its software. These were essentially issues of law which
could almost certainly have been resolved more economically by expert
determination or, at the very worst, by their trial as preliminary issues.
Although the
Pre-Action Protocol for Construction and
Engineering Disputes had been published long before this dispute
began, and its relevance to computer supply disputes made clear in a number
of articles one of which had been on chambers website since August 2000,
nothing in the
judgment indicates that either party or their advisors referred to that
protocol. Had they done so the above issues are likely to have been
identified either in letters of claim or response or picked up at a
pre-action meeting. Paragraph 5.4 of the Protocol would also have required
the parties to consider in respect of each agreed issue and the dispute as a
whole whether some form of alternative dispute resolution procedure
would be more suitable than litigation, and if so, to endeavour to agree
which form to adopt. Even if they could not have agreed to resolve their
dispute by ADR, they would still have been required to use their best
endeavours to agree ways of saving costs.
The
second important lesson from this litigation is that it is still possible
for suppliers to limit or even liability for misrepresentation or breach of
contract in a computer
supply contract by means of contract terms notwithstanding UCTA so long as
the customer is allowed reasonable redress. In this case, the customer could
have asked for his money back so long as he gave timely notice of rejection
and did so before he had actually gained any benefit from the system. As the
requirement to give timely notice of rejection before any benefit is gained
will often conflict with the countervailing requirement to mitigate loss.
Those acting for customers will have to be astute either to negotiate terms
that preserve the right to reject until after the system has been given a
fair trial wherever possible.

|
|
|||||||||
|
|
![]() |

Important