Legislation
(
Edited and posted by John Antell)
Sale of Goods Act 1979
Supply of Goods and Services Act 1982
Unfair Contract Terms Act 1977

Civil Procedure Rules

CPR Part 60 - Technology and Construction Court Claims
PD-60 - Technology and Construction Court Claims
PD - Protocols
Pre-Action Protocol for Construction and Engineering Disputes

Court Guides

Technology and Construction Court Guide (2nd  edition)

Case Law

Arbitration

Halki Shipping v Sopex Oils
[1997] 1 WLR 1268

Expert Witnesses
Anglo Group Plc v Winther Brown & Co. Ltd.
[2000] EWHC Technology 127 (8 Mar, 2000)

TeCSA (Technology and Constructions Solicitors Association)

Expert Witness Protocol (Version 2)

 

 



 


 

Computer Contracts: Litigation Overview

Jane Lambert

Last updated 26 Feb 2006

Disputes or differences between suppliers and their customers are disturbingly common. In an article entitled "Runaway Projects" that appeared on its website in 2000, KPMG reported that 83% of a group of companies that it had surveyed at the end of the 1990s had experienced some sort of runaway project, that is to say, a computer systems project that had failed significantly to meet its objectives. Of course, only a small fraction of those runaways actually ends in litigation but proceedings had been threatened in 20% of the cases surveyed.

First Requirement - consult an Expert early

The first requirement of anyone involved in a runaway is to seek competent and objective professional advice on what went wrong and what, if anything, can be done to put it right. That usually involves retracing the steps that should have been taken by a systems analyst before the contract was entered. KPMG found that the first 3 of the top 5 causes of project runaways were failure to specify the project objectives fully, bad planning and estimating and the customer's unfamiliarity with the technology. Often there is a technical or commercial solution satisfactory to both parties that a competent systems analyst can identify.

The priority at this stage is to seek such a solution rather than to make a case for compensation. For that reason, advice should be sought from an expert who is used to specifying and supplying systems rather than one who spends a disproportionate amount of time giving expert evidence in court. The danger of instructing an expert who is focussed on litigation rather than technology is illustrated by Anglo Group Plc v Winther Brown & Co. Ltd. [2000] EWHC Technology 127 (8 Mar, 2000) where the evidence of the customer's expert, who had taken a confrontational stance from the start and exaggerated his client's case, was completely disregarded. Useful guidance on selecting and instructing an expert is to be found in the TeCSA Expert Witness Protocol (Version 2)

Making a Claim
As the KPMG statistics mentioned above suggest, it is only in a small proportion of cases that a technical or commercial solution does not exist or one or other party fails to consider it. In those circumstances the parties should look to their contract to see what provision is made for the resolution of disputes. An arbitration clause is usually binding on the parties even in circumstances where it would have been possible under previous legislation to apply for summary judgment on the grounds that there was no real dispute or difference (see Halki Shipping v Sopex Oils [1997] 1 WLR 1268). It has recently become fashionable to insert elaborate clauses requiring disputes to be referred up the management chains of both parties and thereafter to an expert for neutral evaluation before either party resorts to litigation. Where such provisions exist they should be tried but the court will refuse to stay proceedings if they are likely to waste time and lead nowhere as in Halifax Financial Services Ltd. v Intuitive Systems Ltd. [1999] 1 All ER Comm.

Pre-Action Negotiations
Although there is not yet a pre-action protocol for computer supply disputes, para 4.1 of the Practice Direction - Protocols provides:

"In cases not covered by any approved protocol, the court will expect the parties, in accordance with the overriding objective and the matters referred to in CPR 1.1(2)(a), (b) and (c), to act reasonably in exchanging information and documents relevant to the claim and generally in trying to avoid the necessity for the start of proceedings"

Moreover, the Pre-action Protocol for Construction and Engineering Disputes, while not expressly including computer supply disputes, provides guidance as to how pre-action negotiations should be conducted.

Aim of the Construction and Engineering Protocol
The general aim of the Protocol is to ensure that before court proceedings commence:

"(i) the claimant and the defendant have provided sufficient information for each party to know the nature of the other’s case;
(ii) each party has had an opportunity to consider the other’s case, and to accept or reject all or any part of the case made against him at the earliest possible stage;
(iii) there is more pre-action contact between the parties;
(iv) better and earlier exchange of information occurs;
(v) there is better pre-action investigation by the parties
(vi) the parties have met formally on at least one occasion with a view to:
- defining and agreeing the issues between them; and
- exploring possible ways by which the claim may be resolved;
(vi) the parties are in a position where they may be able to settle cases early and fairly without recourse to litigation; and
(vii) proceedings will be conducted efficiently if litigation does become necessary."

Letter of Claim
Para 3 of the Pre-action Protocol requires the claimant or his solicitor to each proposed defendant (if appropriate to his registered address) a copy of a letter of claim that contains the following information:
(i) the claimant’s full name and address;
(ii) the full name and address of each proposed defendant;
(iii) a clear summary of the facts on which each claim is based;
(iv) the basis on which each claim is made, identifying the principal contractual terms and statutory provisions relied on;
(v) the nature of the relief claimed: if damages are claimed, a breakdown showing how the damages have been quantified; if a sum is claimed pursuant to a contract, how it has been calculated; if an extension of time is claimed, the period claimed;
(vi) where a claim has been made previously and rejected by a defendant, and the claimant is able to identify the reason(s) for such rejection, the claimant’s grounds of belief as to why the claim was wrongly rejected;
(vii) the names of any experts already instructed by the claimant on whose evidence he intends to rely, identifying the issues to which that evidence will be directed.

Defendant's Response
The defendant has 14 days in which to acknowledge the letter of claim under para 4.1 of the Pre-Action Protocol.

Preliminary Objection
If the defendant objects to the claim on the grounds that:
(1) the court lacks jurisdiction,
(2) the matter should be referred to arbitration, or
(3) the defendant named in the letter of claim is the wrong defendant,
it should make its objection known within 28 days of receipt of the letter of claim (para 4.2.1). Failure to do so may be taken into account when the court decides the question of costs but it will not prevent the defendant from raising those objections at any time.
 the plaintiffs relied on Intuit's skill and judgment in selecting the software.

Letter of Response
The defendant must also respond in writing within 28 days, or such other period as the parties may reasonably agree up to a maximum of 4 months, if it contests the claim on substantive grounds. Para 4.3.1 requires the defendant to send a letter of response. to the claimant containing the following information:
(i) the facts set out in the letter of claim which are agreed or not agreed, and if not agreed, the basis of the disagreement;
(ii) which claims are accepted and which are rejected, and if rejected, the basis of the rejection;
(iii) if a claim is accepted in whole or in part, whether the damages, sums or extensions of time claimed are accepted or rejected, and if rejected, the basis of the rejection;
(iv) if contributory negligence is alleged against the claimant, a summary of the facts relied on;
(v) whether the defendant intends to make a counterclaim, and if so, giving the information which is required to be given in a letter of claim by para 3 (iii) to (vi) of the Protocol;
(vi) the names of any experts already instructed on whose evidence it is intended to rely, identifying the issues to which that evidence will be directed
Should the defendant fail to respond within such time the claimant may commence proceedings without further compliance with the protocol (para 4.3.2).

Claimant's Reply
The claimant has the same amount of time to respond to any counterclaim as allowed to the defendant to respond to the letter of claim (para 4.4).

"Without Prejudice" Meeting
A "without prejudice" meeting should take place as soon as possible after receipt by the claimant of the defendant’s letter of response, or (if the claimant intends to respond to the counterclaim) after receipt by the defendant of the claimant’s letter of response to the counterclaim. The aim of such meeting is to agree what are the main issues in the case, to identify the root cause of disagreement in respect of each issue, and to consider whether, and if so how, the issues might be resolved without recourse to litigation. If litigation is unavoidable, the parties should consider what steps should be taken to ensure that it is conducted in accordance with the overriding objective (para 5.2).

Identification of Issues
If the parties are unable to agree on a means of resolving the dispute other than by litigation they should use their best endeavours to agree
(i) whether, if there is any area where expert evidence is likely to be required, a joint expert may be appointed, and if so, who that should be; and (so far as is practicable);
(ii) the extent of disclosure of documents with a view to saving costs; and
(iii) the conduct of the litigation with the aim of minimising cost and delay;
thereby saving time and costs at the case management stage (para 5.5).

What can be mentioned to the Court
Any party attending such meeting shall be entitled to disclose to the court, that the meeting took place, when it took place and who attended it, the identity of any party who refused to attend, and the grounds for such refusal or if the meeting did not take place, why not; and any agreements concluded between the parties (paragraph 5.6). These are matters that the court can take into account under CPR 44.3 when deciding costs.

Commencing Proceedings

A computer supply dispute is likely to involve issues or questions that are technically complex within the meaning of CPR 60.1 (3) and is therefore apt to be brought in that court. Para 3.2 of PD60 requires the claim form to be marked "Technology and Construction Court." There is now a TCC list in the Central London and other county courts attached to a High Court District Registry. If the claim is brought in the Royal Courts of Justice it will be assigned to a judge ("the assigned judge") who will have primary responsibility for its case management.

Case Management
The court will fix a case management conference within 14 days of the filing of an acknowledgment of service, the filing of a defence; or the date of an order transferring a claim to a TCC, whichever happens first (para 8.1 of PD60). When the court notifies the parties of the date and time of the case management conference, it will at the same time send each party a case management information sheet and a case management directions form.

Not less than 2 days before the case management conference, each party must file and serve on all other parties completed copies of the case management information sheet and case management directions for; and an application notice for any order which that party intends to seek at the case management conference, other than directions referred to in the case management directions form. Parties are encouraged to agree directions to propose to the court by reference to the case management directions form. Should any party fail to file or serve the case management information sheet and the case management directions form by the date specified, the court may impose such sanction as it sees fit and either proceed with or adjourn the case management conference.

The directions given at the case management conference will normally include the fixing of dates for any further case management conferences, a pre-trial review, the either the trial or the trial of preliminary issues.

Pre-Trial Review
When the court fixes the date for a pre-trial review it will send each party a pre-trial review questionnaire and a pre-trial review directions form. Each party must file and serve on all other parties completed copies of the questionnaire and form not less than 2 days before the date fixed for the pre-trial review. As with the case management conference, parties are encouraged to agree directions to propose to the court by reference to the pre-trial review directions form. At the pre-trial review, the court will give such directions for the conduct of the trial as it sees fit.

Trial
Wherever possible the trial of will be heard by the assigned judge which may take place at any place where there is a TCC judge available..
 


HomeCultureBrandsTechnologyIndustriesSite IndexContact

Information and Communications

Computer Contracts

Intellectual PropertyData Protection

 

 

Relevant Articles

Jane Lambert

Computer Systems

Jane Lambert

Information and Communications Technology: Computer Contracts

Jane Lambert

Litigation Overview

Jane Lambert

New TCC Guide takes Effect from 5 Oct 2005

Formation of Contracts

Jane Lambert

Vogon International Ltd. v Serious Fraud Office

Jane Lambert

DMA Financial Solutions Ltd v BaaN UK Ltd

Maintenance Contracts: Duty to maintain in Perpetuity

Jane Lambert

Harbinger UK Ltd. v GE Information Services Ltd.

Jane Lambert

SAM Business Systems Limited v Hedley & Co.

Consequences of Repudiation

Jane Lambert

Crowther v Brownsword and Another

Royalties: Obligation to maintain Records

Jane Lambert

Columbia Tristar Home Video (International) Inc. v Polygram Film International BV

Tenders

Raymond Henley

Countrywide Communications Limited v ICL Pathway Limited and International Computers Limited


 

 

 
               

 
               

Important